After a joint inspection by a respected Edinburgh structural engineer and ourselves, it was decided that the spire and steeple required a five phase contract to remedy the defects found.
These phases were:
- Removing all the cement pointing from the spire and bell chamber windows.
- Re-pointing the spire with lime mortar.
- Re-pointing the bell chamber windows with lime putty.
- Cutting out all suspect masonry and building in new stone (indenting).
- Fitting cramps and dowels to all the joints in the ornate stonework sections of the spire (to prevent any further movement).